Rig Move Planning: How Long Moves Take and What They Cost
Rig moves sit between every well in a pad program, and they are where schedule slips and safety incidents quietly pile up. A move that runs long eats days out of the drilling calendar at the full contract day rate, with nothing drilled in return. Understanding how moves are planned, where the hours go, and what a realistic move actually costs is the difference between a tight pad schedule and a program that bleeds money before the bit turns.
Why the Move Is Part of the Well Cost
Operators and drilling contractors treat the rig move as a line item, but it behaves more like a second well cost. The rig is off line, the crew is on standby pay or moving, and the next location is not making hole. Day rates do not pause while the mast goes down and the trucks line up. FlexRig fleets logged average day rates around $28,500 in 2025 with roughly 60 percent of U.S. deployments going to the Permian Basin, so a single unplanned extra move day on that fleet is a five-figure hit before any other cost is counted.
The move is also a safety exposure. Rig moves accounted for 37 percent of incidents in a 2018 drilling contractor review, more than any other phase of operations. The pattern has not changed much since. Heavy lifts, road transit, and rig-up work at the new pad concentrate risk into a few intense days, which is why disciplined crews treat the move as a procedure with a checklist, not as an improvised scramble.
What a Well-to-Well Move Looks Like
A pad-to-pad move has four phases, and each one has its own failure modes:
- Preparation: road surveys, permits, crane and truck bookings, pad inspection, matting and approach verification.
- Rig-down: mast lowering, securing blocks and lines, skidding or lifting the substructure, segregating pipe racks and auxiliary equipment.
- Transit: moving the drawworks, mast, substructure, mud system, tanks and support equipment in a coordinated convoy.
- Rig-up: spotting the rig, raising the mast, hooking utilities, pressure testing BOPs, and commissioning systems before the first joint of pipe.
Skid moves within a single pad can be done in a day or less, since the rig moves on rails rather than on trucks. Full well-to-well moves take longer. A published mobilization case study cut move duration from 34 days to 13 days by applying project management controls, which shows how much slack typical moves carry and how much a disciplined process can recover.
Where the Hours Go
Most move delays do not come from the physical lifting. They come from the pieces around it:
- Waiting on road permits or weather windows before the convoy can run.
- Pad not ready: location surveys incomplete, matting short, approach roads not stable.
- Equipment staged wrong, so trucks make extra trips or cranes sit idle.
- Crew change timing that leaves the move shorthanded at the critical lift.
- Commissioning surprises at rig-up, especially BOP test failures that were not caught during rig-down.
Each of these is a coordination problem, and coordination is exactly what a written move plan with named owners, staged equipment and a single move coordinator fixes. The operations resources library has more on building move checklists, and the glossary covers the rig-up and rig-down terminology crews use on location.
How Fast Is Fast Enough
Industry target language talks about 24-hour moves, and some operators push crews to hit that number on routine pad-to-pad transfers. The realistic envelope depends on rig class, distance, and how many loads the spread needs:
- Small service rigs and workover units: one to two days for a local move.
- Mid-size land rigs on a pad program: two to four days for a well-to-well move with a full spread.
- Large high-spec rigs moving between fields: a week or more including permits and long-haul transit.
The goal is not to hit an arbitrary number. It is to make the move predictable, so the next spud date holds. A crew that moves in four days every time is easier to plan around than one that sometimes does three and sometimes takes six. Predictability is what lets the operations team commit to the drilling schedule and keep the day rate economics on plan.
Planning the Next Move Before the Current One Ends
The highest-leverage move practice is starting the next move plan while the current well is still drilling. That means road surveys and pad readiness checks run in parallel with the last few stands, permits are filed early, and the move coordinator is named before total depth is reached. Contractors who do this consistently report fewer weather surprises and faster rig-up at the next location.
Move performance should also be measured like any other drilling KPI: planned versus actual days, incident rate per move, and cost per move day. What gets tracked gets improved, and a move metric is the fastest way to see whether a pad program is really gaining or quietly giving days back.
Plan the Rig Calendar, Not Just the Well
Rig moves are the hidden schedule driver in every pad program. They are predictable enough to plan and expensive enough to matter, and the crews that treat them as a disciplined procedure protect both the calendar and the safety record. The 37 percent incident share and the day-rate math make the case: a move is not downtime between wells, it is a phase of the well cost that deserves the same rigor as the drilling itself.
If your team is juggling rig schedules, move logistics and ticket flow by hand, book a working session with the OpsFlo operations team to see how field operations software keeps the whole program visible from pad to invoice. Book a call with the OpsFlo team here.
Planning a move in the patch?
Book a working session with OpsFlo to map crews, tickets and billing for your operation.
Book a session